Attention: Please take a moment to consider our terms and conditions before posting.

What's the latest on the redevelopment of the Training Ground?

14567810»

Comments

  • I know that a large part of a construction projects costs is spent before anything much above ground can be seen. Which is why construction project managers measure progress by checking if the budget is being spent to plan, rather than what is visible. Clearly the training ground budget was never funded, and the necessary work has proceeded piecemeal on the back of transfer windfalls, but if and when the balance of money is released, the buildings will probably spring up quite quickly.

    The sole problem I suggest is Roland's refusal to fund the project as promised, rather than lack of effort or management control.

    In his own inimitable fashion...what's new ?

    The true definition of a mucking fuddle.
  • I'm not gonna defend anybody in the regime but the role of contractors in construction projects and their duration is pivotal.
    I was involved, on the client side, a dozen or more years ago, in the rebuilding of a sports pavilion/changing rooms/function suite. Contract agreed, fees agreed, schedule agreed, etc etc. At each stage when the contractor could, under the standard terms, apply for more time, it applied for more time. At the latest possible date in the original contract, the builder submitted that it had finished and the site was fit to be handed back to the client. That was rejected by the PM, surveyors, architect and the local authority. The contractor then simply failed to respond to any correspondence, secure in the knowledge our only recourse would be through solicitors and the courts. In short ours was as small a job as they ever did and their main big earner contract had just gone very badly for them, they'd lowballed on some big development of flats and crippling cash flow problems had come home to roost.
    By the time we were able to engage replacements; an 18 month project ended up taking 30 and the last 15% of the works effectively cost 50% of the total. The original builder walked away from the 10% retention it might have been due, because it simply wasn't enough to worry about.

    With charlton's training ground my money's still on incompetence, penny-pinching and prevarication by the client holding things up rather than contractors dragging their feet.
  • HarryLime said:

    Addickted said:

    Swisdom said:

    To answer the original post.

    Two safety helmeted men with clip boards seen yesterday morning approx 10.30 looking in a hole adjacent to small trench. Third one talking at length on mobile phone....out of earshot of the two already mentioned.
    Two further men, also helmeted, seen eating bacon sarnies one with a can of Coke the other with a can of shandy.
    Mini digger seen parked up nearby with donkey jacketed man sitting inside rolling what looks like a fag......though could be a joint.
    Youth in camouflage jacket standing next to digger smoking and drinking can of Special Brew, second youth eating a pot noodle and sausage roll whilst leaning on a shovel.
    Two other men, one on mobile phone with fag wearing a Chelsea shirt who occasionally sniffs and gobs, second reading The Sun whilst leaning up against a wall eating bag of cheese and onion crisps.
    In other words, normal work in progress.

    Thankfully none of the descriptions match those of our guys there yesterday who were working their arses off pullling and installing many hundreds of meters of HV cable. Power will be sorted soon :wink:
    But start on site was supposed to be 12th October 2015.

    The 'lead in' time of 14th September 2015 would be to arrange with the service providers to provide their costings for the works, whilst your builders and specialist carried out the excavations, trenches and first fixes, ready for those providers to come in and carry out their installations and connections where necessary.

    Are you saying we are now starting from square one? Can none of the existing services be utilised? Surely there must have been a three phased supply already on site?

    There is simply no excuses as to why this hasn't moved forward, despite your defence of the programme. Nothing but lies, obfuscation and atrocious management, which is typical of this regime. If this was the real world the Project Manager would have been sacked about a year ago, particularly as we were informed this was his primary focus until the academy was complete.

    What the hell does he do?
    Sandwiches don't make themselves
    Pot noodles do!
  • The last Relegation threw a big spanner in the works and set everything back
  • Haven't read through the thread so apologies if this has been answered but does anyone know what's happening with the memorial garden? Daughter was at training ground a few weeks ago and said it's no longer where it was
  • The Shard started work at about the same time as the training ground project
  • The Shard started work at about the same time as the training ground project

    Final planning consent was not granted in September 2015 so not true.

    Contract negotiations would need to be finalised after this followed by mobilisation.
  • Haven't read through the thread so apologies if this has been answered but does anyone know what's happening with the memorial garden? Daughter was at training ground a few weeks ago and said it's no longer where it was

    The Pierre Bolangi memorial garden? I was there with Mrs FF and saw the hardwork she and her husband had put in that was some 3 years ago now. The reopening we were told ( please correct me if I get this wrong Mrs F) was being rescheduled for the following month. (November) I was talking about this a bit later with someone else I was surprised to hear. "If it happens at all under this lot" That was when the lying started and I stopped going.
  • Sponsored links:


  • cafc999 said:

    I'm not gonna defend anybody in the regime but the role of contractors in construction projects and their duration is pivotal.
    I was involved, on the client side, a dozen or more years ago, in the rebuilding of a sports pavilion/changing rooms/function suite. Contract agreed, fees agreed, schedule agreed, etc etc. At each stage when the contractor could, under the standard terms, apply for more time, it applied for more time. At the latest possible date in the original contract, the builder submitted that it had finished and the site was fit to be handed back to the client. That was rejected by the PM, surveyors, architect and the local authority. The contractor then simply failed to respond to any correspondence, secure in the knowledge our only recourse would be through solicitors and the courts. In short ours was as small a job as they ever did and their main big earner contract had just gone very badly for them, they'd lowballed on some big development of flats and crippling cash flow problems had come home to roost.
    By the time we were able to engage replacements; an 18 month project ended up taking 30 and the last 15% of the works effectively cost 50% of the total. The original builder walked away from the 10% retention it might have been due, because it simply wasn't enough to worry about.

    With charlton's training ground my money's still on incompetence, penny-pinching and prevarication by the client holding things up rather than contractors dragging their feet.

    Tony Keohane stated that work was delayed due to relegation. When pressed he wouldn't commit to an actual completion date.
    He did. I was there when he said it.
  • Addickted said:

    Wow Fanny, just wow.

    This is a perfect example of how everything that is so important about 'being Charlton' means absolutely nothing to this mob who are pretending to run the Club.

    If there is anything left in the fighting fund once these philistines have left us, I cannot think of a more fitting way for it to be used, than on the memorial garden.

    Amazing, Addickted had a good idea
  • A broken clock is right twice a day too.
  • A broken clock is right twice a day too.

    What if it’s a digital LCD one and the numbers don’t light up ?
  • Addickted said:

    Wow Fanny, just wow.

    This is a perfect example of how everything that is so important about 'being Charlton' means absolutely nothing to this mob who are pretending to run the Club.

    If there is anything left in the fighting fund once these philistines have left us, I cannot think of a more fitting way for it to be used, than on the memorial garden.

    Bless you, @Addickted.

    Let's wait & see what happens with the rebuild under new owners.
  • Thanks for the update Fanny. Had seen that the bust had gone some time ago and assumed (hoped) it had been put away for safe keeping during the works, but plinth and surrounding garden was there at least until the summer break.
  • Maybe Karl can provide a training ground update tomorrow night?
  • Fumbluff said:

    Maybe Karl can provide a training ground update tomorrow night?

    What's he doing tomorrow night?
  • Sponsored links:


  • Thanks for the update Fanny. Had seen that the bust had gone some time ago and assumed (hoped) it had been put away for safe keeping during the works, but plinth and surrounding garden was there at least until the summer break.

    Really ! Thanks, RRH.

    That confirms what we were told then.

    Wonder why the removal of plants wasn't carried out after all ....
  • Thanks for the update Fanny. Had seen that the bust had gone some time ago and assumed (hoped) it had been put away for safe keeping during the works, but plinth and surrounding garden was there at least until the summer break.

    Really ! Thanks, RRH.

    That confirms what we were told then.

    Wonder why the removal of plants wasn't carried out after all ....
    Presumably because you couldn’t turn up and do it for them.
Sign In or Register to comment.

Roland Out Forever!